NOTICE OF STUDY
COMPLETION
Pickering Parkway Improvements
Municipal Class Environmental Assessment and Preliminary Design
Schedule “B”
from Liverpool Road to west of Glenanna Road
THE STUDY
The City of Pickering has
completed a Class Environmental Assessment (EA) Study for
improvements to Pickering Parkway from Liverpool Road to west of
Glenanna Road as shown on the study area map below. A parking
structure is proposed to be built inside the Pickering Town
Centre on the south-western portion of the parking area and is
expected to increase vehicular operations along Pickering
Parkway. Based on the identified need to address capacity
issues, the Study recommends a preferred solution which consists
of the following:
- Implement a signalized
intersection at the southwest corner of the Pickering Town
Centre (PTC);
- Implement dual westbound
left turn lanes from Pickering Parkway to Liverpool Road;
- Relocate the existing PTC
access off Pickering Parkway (adjacent to the Esso gas
station) further east of Liverpool Road and eliminate the
left out movement;
- Implement additional traffic
lanes on Pickering Parkway east of Liverpool Road; and
- Construct a new right in /
right out access off Liverpool Road north of Pickering
Parkway

THE PROCESS
The study was conducted in
accordance with the planning and design process for Schedule “B”
projects as outlined in the Municipal Engineers Association
"Municipal Class Environmental Assessment" document (October
2000, as amended in 2007), which is approved under the
Ontario Environmental Assessment Act.
A project file has been prepared,
which documents the Class EA planning and decision-making
process. The project file is available for public review for 30
days beginning on October 27, 2010 at the following location:
City of Pickering
Clerk’s Office
One The Esplanade, Pickering, ON
Monday to Friday 8:30 am to 4:30 pm
Please provide written comments
to the City of Pickering by Friday, November 26, 2010. If
concerns regarding this project cannot be resolved in discussion
with the City, a person or party may request that the Minister
of the Environment make an order for the project to comply with
Part II of the Environmental Assessment Act (referred to
as a Part II Order). Requests for a Part II Order must be
received by the Minister in writing at the following address:
The Honourable
John Wilkinson
Minister of the Environment
77 Wellesley Street West
11th Floor, Ferguson Block
Toronto, Ontario, M4V 1P5
A copy of the request must also
be sent to the Division Head of Engineering Services identified
below. If no requests are received by Friday, November 26, 2010,
the City will proceed with detailed design and construction of
the preferred alternative. If there are any additional questions
or concerns, please feel free to contact either of the project
representatives below:
|
Mr. Richard Holborn, P. Eng
Division Head
Engineering Services Division
City of Pickering,
One The Esplanade
Pickering, ON L1V 6K7
Phone: 905-420-4660 x 2049
rholborn@cityofpickering.com |
Mr. Andreas Houlios, B.E.S
Environmental Planner
IBI Group
360 James Street North
Hamilton, ON L8L 1H5
Phone: 905-546-1010
Fax: 905-546-1011
andreas.houlios@ibigroup.com |
This Notice
was first issued on October 27, 2010 |