Unofficial Bid Results
|
| The following
information is as read out at the public tender opening. The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications. |
|
|
The following unofficial Bid results as read out at the public
tender opening July 30, 2008 for:
Subject Tender No.
T-15-2008
Tender for Tennis Court Roof Replacement – Pickering
Recreation Complex |
| Bidder |
Total
Tendered Amount
BASE BID |
|
Triumph Aluminum & Sheet Metal Inc. |
$190,890.00 |
|
Solar Roofing & Sheet Metal Ltd. |
$188,055.00 |
|
Semple-Gooder Roofing Ltd. |
$245,601.30 |
|
Viana Roofing & Sheet Metal Ltd. |
$435,750.00 |
|
Provincial Industrial Roofing & Sheet Metal |
$250,958.40 |
|
Flynn Roofing |
$315,903.00 |
|
Atlas-Apex Roofing Ltd. |
Unable to Bid |
|
John McLellan Contracting Inc. |
Unable to Bid |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening July 23, 2008 for:
Subject Tender No.
T-11-2008
Tender for Humidification System Replacement – Pickering
Civic Complex |
| Bidder |
Total
Tendered Amount |
|
CANADIAN TECH AIR |
$244,386.00 |
|
BIRD MECHANICAL |
$252,000.00 |
|
GIMCO LTD. |
$237,897.00 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening July 9, 2008 for:
Subject Tender No.
T-2-2008
Tender for Pickering Recreation Complex – Double Squash Courts and Aerobics Studio |
| Bidder |
Total
Tendered Amount |
| BWK CONSTRUCTION |
$3,321,150.00 |
| STEELCASE CONSTRUCTION |
$3,460,800.00 |
| JASPER CONSTRUCTION |
$3,930,150.00 |
| GERR CONSTRUCTION |
UNABLE TO BID |
| GAY COMPANY LIMITED |
UNABLE TO BID |
| STRUCT CON CONSTRUCTION |
UNABLE TO BID |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
| The following unofficial Bid results as read out at the public
tender opening July 7, 2008 for:
Subject Tender No. T-12-2008
Tender for Artificial Turf – Bay Ridges Kinsmen Park |
| Bidder |
Total
Tendered Amount |
| Rutherford Contracting |
$625,047.05 |
| Dol Turf Restoration Ltd. |
$658,608.55 |
| Dig Con International |
$773,167.50 |
| Pine Valley Enterprises |
$824,570.25 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening July 2, 2008 for:
Subject Tender No. T-10-2008
EASTERN GATEWAY CONSTRUCTION |
| Bidder |
Total
Tendered Amount |
| DIG CON |
$116,075.40 |
| MONTGOMERY
MACEWEN CONTRACTING |
$111,050.49 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening July 2, 2008 for:
Subject Tender No. T-13-2008
Pickering Museum Village Brougham Central Hotel
Construction
Phase 1 - Foundation |
| Bidder |
Total
Tendered Amount |
| Limen
Group |
$219,291.45 |
| Rutherford
Contracting |
$229,950.00 |
| Colonial
Bldg Restoration |
$406,350.00 |
| Roof
Tile Management |
Unable
to Bid |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening June 23, 2008 for:
Subject Tender No. T-3-2008
Energy Recovery Ventilation and Pool Dehumidification System
Dunbarton Indoor Pool - Pickering |
| Bidder |
Total
Tendered Amount |
| No Bids |
--- |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening June 25, 2008 for:
Subject Tender No. T-4-2008
Sheppard Avenue – Road Reconstruction and Storm Sewer Works
view / print PDF |
| Bidder |
Total
Tendered Amount |
| Dagmar
Construction Limited |
$2,491,737.69 |
| Ron
Robinson Limited |
$2,977,816.09 |
| Hard Co
Construction Limited |
$2,977,846.20 |
| Elirpa
Construction & Materials |
$3,769,955.69 |
|
Montgomery MacEwan |
UNABLE TO BID |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening June 18, 2008 for:
Subject Tender No. T-7-2008
Surface Treatment |
| Bidder |
Total
Tendered Amount |
| Miller
Paving Limited |
$732,320.93 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening June 11, 2008 for:
Subject Tender No. T-8-2008
Pickering Lawn Bowling Greens Phase II |
| Bidder |
Total
Tendered Amount |
| MELFER
CONSTRUCTION |
$465,423.00 |
| CAMBIUM
SITE CONTRACTING |
$522,885.35 |
|
RUTHERFORD CONTRACTING |
$550,747.44 |
|
MONTGOMERY MACEWAN |
$629,046.81 |
| DIG CON
CONSTRUCTION |
$653,638.44 |
| MELROSE
PAVING COMPANY |
UNABLE TO BID |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening June 25, 2008 for:
Subject Tender No. T-9-2008
Path Extension to Bus Loop at Sunbird Trail Park
view / print PDF |
| Bidder |
Total
Tendered Amount |
| Dig Con
International Limited |
94,398.15 |
|
Montgomery MacEwan |
96,727.48 |
| Mopal
Construction |
98,322.00 |
| Elirpa
Construction |
108,991.47 |
|
Royalcrest Paving & Contracting |
115,374.00 |
| Aloia
Bros Concrete Contractors |
126,479.85 |
| JPK
Contracting |
99,400.35 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
|
The following unofficial Bid results as read out at the public
tender opening April 9, 2008 for:
Subject Tender No. T-1-2008
Tender for Don Beer Arena Rink 2 Renovations
Closing – April 9, 2008 |
| Bidder |
Total
Tendered Amount |
| A Con
Construction |
$597,250.00 |
Frank
Pellegrino
General Contracting Ltd. |
$607,100.00 |
Jeffrey
G. Wallans
Construction Ltd. |
$656,145.00 |
| Canada
Construction |
$669,900.00 |
| JMX
Contracting Inc. |
$765,450.00 |
| The
information is strictly preliminary, pending review and
verification of conformance to terms, conditions and
specifications |
Return to Supply & Services Overview
|