ROADS |
|
Project Name
|
Project Description
|
Project Schedule
|
Contractor / Consultant
|
Browning Avenue
|
Storm sewer replacement and installation of oil grit
separator |
|
Survey completed
Detail design being prepared |
Liverpool Road
|
Road reconstruction and storm sewer from Wharf Street to
Annland Street; includes nautical streetscaping in boulevard
and lighting |
Summer 2012 |
Detail design required |
Welrus Street
|
Storm sewer installation, road reconstruction to an urban
standard; sidewalk installation |
Spring 2012 |
Topographical survey being completed by Omari Mwinyi
Surveying |
Westshore Boulevard
|
Road reconstruction from Oklahoma Drive to Sunrise Avenue |
Summer 2012 |
Contractor TBD
Detail design required |
Wharf Street
|
Sidewalk construction on north side of Wharf Street |
Spring 2011 |
Project completed |
|
Whitevale Bridge Replacement |
Design & Schedule B, Class EA |
Spring 2012 |
SRM Associates |
|
STREET LIGHTING / TRAFFIC SIGNALS |
|
Project Name
|
Project Description
|
Project Schedule
|
Contractor / Consultant
|
|
Bay Ridges Phase
I |
Streetlight
replacement program in conjunction with Veridian Project |
TBD 2012 |
AECOM |
|
Dixie Road |
Streetlight
replacement from Kingston Road to Finch Avenue |
Spring 2012 |
Detail design
provided by Nexgen Utilities |
|
Granite Court at
Sandstone Manor |
Intersection
Pedestrian Signal |
Fall 2011 |
Project
completed |
|
Squires Beach
Road at Clements Road |
Signalization of
intersection at Clements & Squires Beach Road |
Fall 2012 |
Region reviewing property requirements
|
|
Waterfront Trail |
Installation of
pedestrian lights on the Waterfront Trail along Annland
Street |
Summer 2012 |
Design completed by Kirkland Engineering; Staff to review
|